Sichuan Dazhou sodium ion battery industry comprehensive project progresses smoothly

0
The sodium-ion battery industry comprehensive project in the Eastern Economic Development Zone of Dazhou, Sichuan is progressing steadily. At present, 80% of the civil construction of the PACK plant has been completed, and 70% of the steel structure has been completed. It is expected that the construction will be completed and the commissioning of two equipment lines will be carried out before the end of the year. The project is jointly invested by Liaoning Xingkong Sodium Battery Co., Ltd., Liaoning Hongcheng Power Supply Co., Ltd. and the Management Committee of the Eastern Economic Development Zone of Dazhou, with a total amount of 11.5 billion yuan. The project mainly covers sodium-ion batteries, PACK integration, energy storage power stations, 110KV substations, distribution lines, smart grid management systems, etc.