Xpeng Zhaoqing Factory Launches New Model Production Line Transformation Project

0
Recently, Xiaopeng Motors Zhaoqing Factory held a launching ceremony for the production line transformation of a new model project. The project aims to upgrade the existing vehicle production line to prepare for the production of new models, thereby increasing production capacity. The total investment of the project exceeds 100 million yuan, and the scope of transformation includes the production lines and logistics equipment and facilities of the four major workshops of stamping, welding, painting and assembly. The entire transformation process is expected to last about 20 days, and all transformation projects are planned to be completed before February 9, and the overall production line commissioning work will be completed by the end of February.