Weilan New Energy's 5 major bases

2024-05-16 00:00
 135
Beijing Fangshan Base Headquarters: R&D base + homogeneous base, production capacity planning: 6GWh, building area: 70 acres + 151 acres, production time: 2025; Shandong Zibo Base: Energy Storage Base, production capacity planning: 20GWh energy storage, building area: 500 acres, production time: September 2023 (Phase I); Zhejiang Shaoxing Slurry Base: Guzhi Battery Key Materials and Guzhi Battery Production Base Dingri, production capacity planning: 10,000 tons, building area: 15,000 square meters7, production time: the end of 2023; Zhejiang Huzhou Base: Automobile Power Base, production capacity planning: 2GWh + 20GWh, building area: 70 acres + 500 acres, production time: March 2022, the end of 2024; Jiangsu Liyang Base: Pilot Line + Small Power Base, production capacity planning: 0.2GWh, building area: 38 acres, production time: August 2020.