The main construction of the Times Nebula Energy Storage Industrial Park has been completed and is expected to be fully operational by the end of 2024

263
The Times Nebula Energy Storage Industrial Park, built by Fujian Times Nebula Technology Co., Ltd. with an investment of 515 million yuan, has completed the main construction and is currently in the acceptance stage. The industrial park covers an area of about 87 acres, with a total construction area of about 130,000 square meters, equipped with 13 production lines, including 9 automated PACK production lines. It is expected that after it is put into production, the annual production capacity will reach about 12 GWh, with an annual output value of about 6 billion yuan.